No. | DELIVERABLE NAME | DELIVERABLE SHORT DESCRIPTION | WP No. | DEL. LEAD PARTICIPANT | TYPE | DISS. LEVEL | DELIVERY |
D1.1 |
Project management guide |
Project management guide [M3; ARC; R; PU] Report that defines the project monitoring processes, conflict, risk management, deliverable review procedures and templates to be used by the consortium for an efficient and effective project implementation. DOI 10.5281/zenodo.11097958 (Accepted). |
WP1 |
ARC |
R |
PU |
M3 |
D1.2 |
Data management plan (DMP) |
Data management plan (DMP) [M6; ARC; R; PU] Report that defines how the project results will be curated and published (where applicable), ensuring a basis for fuelling the relevant project WPs. DOI 10.5281/zenodo.11098069 (Accepted). |
WP1 |
ARC |
R |
PU |
M6 |
D2.1 |
OS-aware RRA approaches landscape report |
OS-aware RRA approaches landscape report [M8; TSV; R; PU] A landscape analysis report that identifies common OS RRA practices, qualitative and quantitative data priorities, and associated implementation obstacles, making explicit recommendations on structuring qualitative assessment data relevant to assessment practices and enabling infrastructure. DOI 10.5281/zenodo.11098095 (Accepted)
|
WP2 |
TSV |
R |
PU |
M8 |
D2.2 D2.3 |
OSAF |
OSAF [M10, M24; CWTS; O; PU] The Open Science Assessment Framework, including Openness Profile templates and the Open Science Assessment Registry (OSAR). DOI 10.5281/zenodo.11091512 (Accepted) |
WP2 |
CWTS |
O |
PU |
M12 M34 |
D2.4 |
OSAF specifications for pilots |
OSAF specifications for pilots [M15; CWTS; R; PU] Documentation of the specification of the OS-aware RRA protocols required for the pilots. |
WP2 |
CWTS |
R |
PU |
M22 |
D3.1 |
Tools and services landscape report |
Tools and services landscape report [M8; ARC; R; PU] A report on the results of the landscape analysis for existing tools and services for community-led curation/annotation and for monitoring the use and uptake of research outputs and OS practices. DOI 10.5281/zenodo.11091567 (Accepted) |
WP3 |
ARC |
R |
PU |
M8 |
D3.2 D3.3 |
Tools and services |
Tools and services [M20, M34; OAIRE; OTHER; PU] The community-led curation/ annotation and monitoring tools and services that have been developed. DOI 10.5281/zenodo.13619175 (Submitted) |
WP3 |
OAIRE |
OTHER |
PU |
M20 M34 |
D4.1 D4.2
|
Infrastructure architecture |
Infrastructure architecture [M8, M20; CNR; R; PU] A living report on the architecture of the Federated Open Metrics Infrastructure. D4.1 DOI 10.5281/zenodo.11091592 (Accepted) D4.2 DOI 10.5281/zenodo.13618530 (submitted)
|
WP4 |
CNR |
R |
PU |
M8 M20 |
D4.3 D4.4 D4.5 |
Federated Open Metrics Infrastructure (FOMI) |
Federated Open Metrics Infrastructure (FOMI) [M12, M20, M34; OAIRE; OTHER; PU] The implemented Federated Open Metrics Infrastructure. D4.3 DOI 10.5281/zenodo.11091628 (Accepted) D4.4 DOI 10.5281/zenodo.13617814 (Submitted)
|
WP4 |
OAIRE |
OTHER |
PU |
M12 M20 M34
|
D5.1 |
Report on pilot setup, current practices & initial requirements |
Report on pilot setup, current practices & initial requirements [M8;CSC; R; PU] Report on pilot preparation, setup, and methodologies of piloting activities. It will also leverage the analysis in D2.1 to describe the current status on how research assessment (practices, tools, challenges) is performed by the pilot owners, positioning them in the research landscape and identifying initial requirements for WP2, WP3 and WP4. DOI 10.5281/zenodo.11091718 (Accepted).
|
WP5 |
CSC |
R |
PU |
M8 |
D5.2 D5.3 |
Pilot findings and progress report |
Pilot findings and progress report [M20,M32; CSC; R; PU] Detailed description of the activities performed by the pilots and the results achieved. The report also includes lessons learnt from the pilots and the plan for the future period. DOI 10.5281/zenodo.13629146 (Submitted) |
WP5 |
CSC |
R |
PU |
M20 M32 |
D6.1 D6.2 |
Communication, dissemination, and exploitation plan |
Communication, dissemination, and exploitation plan [M6, M30; CNR; R; PU] A report elaborating GraspOS’s strategic planning for the communication, dissemination, and exploitation of the project results. DOI 10.5281/zenodo.10990582 (Accepted).
|
WP6 |
CNR |
R |
PU |
M6 M30 |
D6.3 |
Community engagement and training activities plan |
Community engagement and training activities plan [M6; CWTS; R; PU] A report identifying networks and stakeholders to be involved in this task, strategies and method for participation and content to be discussed. DOI 10.5281/zenodo.11091776 (Accepted). |
WP6 |
CWTS |
R |
PU |
M6 |
D6.4 D6.5 |
Report on C/D/E, community engagement, and training activities |
Report on C/D/E, community engagement, and training activities [M12, M34; CNR; R, PU] A report presenting an overview and assessment of the communication, dissemination, and exploitation activities along with the outcomes of the training courses, the engagement process and a sustainability plan for the community of practice. DOI 10.5281/zenodo.11091850 (Accepted). |
WP6 |
CNR |
R |
PU |
M12 M34
|
D7.1 |
OEI - Requirement No. 1 |
GraspOS aims to build and operate a data infrastructure to support the policy reforms and pave the way toward a responsible research assessment system that embeds OS practices. The project will extend the EOSC ecosystem with tools and services that will facilitate monitoring the use and uptake of various types of research services and outputs (publications, datasets, software).
GraspOS will be assessed in terms of its compliance with the rules of ethics and legal compliance by an Independent Ethics Advisor that is not yet identified in the application. Appoint an Independent Ethics Advisor in the first 6 months of the Project to check researchers personal data usage, AI-assisted data analysis methodologies, cooperation with Non-EU countries etc. DOI 10.5281/zenodo.10653979. |
WP7 |
ARC |
ETHICS |
SENSITIVE |
M6 |
D7.2 |
OEI - Requirement No. 2 |
Report of the Independent Ethics Advisor for the first Reporting Period of the Project. DOI 10.5281/zenodo.10654095.
|
WP7 |
ARC |
ETHICS |
SENSITIVE |
M12 |
D7.3 |
OEI - Requirement No. 3 |
Report of the Independent Ethics Advisor for the second reporting period of the project. |
WP7 |
ARC |
ETHICS |
SENSITIVE |
M36 |